Question text: |
To ask the Secretary of State for Energy Security and Net Zero, what assessment his Department has made of the feasibility of installing a grid connection corridor along the A1 and A421 to enable commercial warehouses in that area to connect rooftop solar |
Is named day: |
false |
Date of holding answer: |
|
Date answered: |
2025-06-17 |
Date answer corrected: |
|
Is holding answer: |
false |
Is correcting answer: |
false |
Answering Member ID: |
4998 |
Answering Member display name: |
Michael Shanks
|
Answering Member handle: |
mgshanks
|
Answering Member Twitter reference: |
@mgshanks
|
Correcting Member ID: |
|
Correcting Member display name: |
|
Correcting Member handle: |
|
Correcting Member Twitter reference: |
|
Answer text: |
Distribution Network Operators are upgrading local electricity distribution networks across Great Britain to enable the connection of low carbon generation, including rooftop solar. For the current electricity distribution price control (RIIO-ED2, 2023-20... |