Heading: |
Solar Power: Business Premises |
Question ID: |
1810615 |
UIN: |
58191 |
House: |
Commons |
Date tabled: |
2025-06-09 |
Asking Member ID: |
3912 |
Asking Member display name: |
Richard Fuller
|
Asking Member handle: |
|
Asking Member Twitter reference: |
Richard Fuller
|
Member interest: |
false |
Question text: |
To ask the Secretary of State for Energy Security and Net Zero, what assessment he has made of the capacity of the National Grid to provide (a) timely and (b) adequate connections in the context of estimated trends in the level of adoption of rooftop sola |
Is named day: |
false |
Date of holding answer: |
|
Date answered: |
2025-06-17 |
Date answer corrected: |
|
Is holding answer: |
false |
Is correcting answer: |
false |
Answering Member ID: |
4998 |
Answering Member display name: |
Michael Shanks
|
Answering Member handle: |
mgshanks
|
Answering Member Twitter reference: |
@mgshanks
|
Correcting Member ID: |
|
Correcting Member display name: |
|
Correcting Member handle: |
|
Correcting Member Twitter reference: |
|
Answer text: |
Ofgem recently made it easier for smaller generation projects (under 5MW in England and Wales) to connect, by removing the requirement for a transmission network impact assessment [1]. For larger projects, the implementation of connections reform will pri... |
Original answer text: |
|
Comparable answer text: |
|
Answering body ID: |
215 |
Answering body name: |
Department for Energy Security and Net Zero |
Tweeted: |
true |