Question text: |
To ask the Secretary of State for Energy Security and Net Zero, what assessment he has made of the potential impact of Ofgem's readiness criteria for the UK data centre sector on growth in that sector. |
Is named day: |
true |
Date of holding answer: |
|
Date answered: |
2025-06-16 |
Date answer corrected: |
|
Is holding answer: |
false |
Is correcting answer: |
false |
Answering Member ID: |
4998 |
Answering Member display name: |
Michael Shanks
|
Answering Member handle: |
mgshanks
|
Answering Member Twitter reference: |
@mgshanks
|
Correcting Member ID: |
|
Correcting Member display name: |
|
Correcting Member handle: |
|
Correcting Member Twitter reference: |
|
Answer text: |
The Government has worked closely with Ofgem and NESO on major reforms to the grid connections process. These reforms are expected to deprioritise up to 500GW of excess generation and storage capacity from the connections queue, freeing up capacity for vi... |