Question text: |
To ask the Secretary of State for Transport, with reference to paragraph 5.83 of the Spending Review 2025, published on 11 June 2025, how much funding has been allocated to progress the next stage of Midlands Rail Hub West. |
Is named day: |
true |
Date of holding answer: |
|
Date answered: |
2025-06-16 |
Date answer corrected: |
|
Is holding answer: |
false |
Is correcting answer: |
false |
Answering Member ID: |
4943 |
Answering Member display name: |
Simon Lightwood
|
Answering Member handle: |
simonlightwood
|
Answering Member Twitter reference: |
@simonlightwood
|
Correcting Member ID: |
|
Correcting Member display name: |
|
Correcting Member handle: |
|
Correcting Member Twitter reference: |
|
Answer text: |
The Chancellor confirmed Midlands Rail Hub is a priority for the Government and £123m has been committed for the next phase of the Programme. |