Land Drainage: Cambridgeshire |
Question ID: |
1785216 |
UIN: |
38726 |
House: |
Commons |
Date tabled: |
2025-03-17 |
Asking Member ID: |
5089 |
Asking Member display name: |
Ben Obese-Jecty
|
Asking Member handle: |
BenObeseJecty
|
Asking Member Twitter reference: |
@BenObeseJecty
|
Member interest: |
false |
Question text: |
To ask the Secretary of State for Environment, Food and Rural Affairs, pursuant to the Answer of 17 March 2025 to Question 36866 on Internal Drainage Boards: Cambridgeshire, what the nature is of the Bevill’s Leam Pumping Station Resilience Works Phase 1; |
Is named day: |
false |
Date of holding answer: |
|
Date answered: |
2025-03-24 |
Date answer corrected: |
|
Is holding answer: |
false |
Is correcting answer: |
false |
Answering Member ID: |
4645 |
Answering Member display name: |
Emma Hardy
|
Answering Member handle: |
|
Answering Member Twitter reference: |
Emma Hardy
|
Correcting Member ID: |
|
Correcting Member display name: |
|
Correcting Member handle: |
|
Correcting Member Twitter reference: |
|
Answer text: |
Bevill’s Leam Pumping Station Resilience Works Phase 1 is a project which is being delivered through Tranche 2A of the Internal Drainage Board (IDB) Fund. This funding is focused on modern replacement and improvements to IDB assets. The Bevill’s Leam proj... |