To ask His Majesty's Government when the current work on the A1's Wentbridge Viaduct started, and when they expect traffic flows to return to normal. |
Is named day: |
false |
Date of holding answer: |
|
Date answered: |
2024-09-23 |
Date answer corrected: |
|
Is holding answer: |
false |
Is correcting answer: |
false |
Answering Member ID: |
4972 |
Answering Member display name: |
Lord Hendy of Richmond Hill
|
Answering Member handle: |
|
Answering Member Twitter reference: |
Lord Hendy of Richmond Hill
|
Correcting Member ID: |
|
Correcting Member display name: |
|
Correcting Member handle: |
|
Correcting Member Twitter reference: |
|
Answer text: |
The original estimate for the Wentbridge Viaduct was £5,403,583, however, at present the expected cost for the works is £16,079,669. The change in costs is due to significant change of scope as additional essential repairs were identified, including but n... |