Heading: |
Sizewell C Power Station |
Question ID: |
1728002 |
UIN: |
HL864 |
House: |
Lords |
Date tabled: |
2024-09-09 |
Asking Member ID: |
3526 |
Asking Member display name: |
Lord Berkeley
|
Asking Member handle: |
|
Asking Member Twitter reference: |
Lord Berkeley
|
Member interest: |
false |
Question text: |
To ask His Majesty's Government what factors will be considered when making a final investment decision in relation to Sizewell C, and whether this decision is dependent on further regulatory approval. |
Is named day: |
false |
Date of holding answer: |
|
Date answered: |
2024-09-23 |
Date answer corrected: |
|
Is holding answer: |
false |
Is correcting answer: |
false |
Answering Member ID: |
2024 |
Answering Member display name: |
Lord Hunt of Kings Heath
|
Answering Member handle: |
lordphilofbrum
|
Answering Member Twitter reference: |
@lordphilofbrum
|
Correcting Member ID: |
|
Correcting Member display name: |
|
Correcting Member handle: |
|
Correcting Member Twitter reference: |
|
Answer text: |
Work continues to secure a Final Investment Decision (FID) for Sizewell C. Any decision to take FID will consider all relevant factors and be supported by the Full Business Case (FBC) and a Value for Money Assessment, in line with HM Treasury’s Green Book... |
Original answer text: |
|
Comparable answer text: |
|
Answering body ID: |
215 |
Answering body name: |
Department for Energy Security and Net Zero |
Tweeted: |
true |